Big Salty Range R.O. Work Projects To Keep R.O. Status
Paint and some other materials/purchased items can and will be provided as needed.
Please log any work on the Range Officer Log form.
- Pick up brass on any bay. Time spent ,bay or bay's brass was picked up on needs to be recorded along with a picture of your brass collection needs to be texted to 801-641-4397 before it will be accepted for range work hours.
- Replace overhead lights in the classroom with LED fixtures that the range will supply as needed.
- Empty garbage cans on all 14 bays and pavilion into the dumpster in the middle of the range.
- Walk around the range and pick up all loose garbage that has been blown around by the wind.
- If you are the only one on the range and there is no live firing going on you can clean garbage off of the back berm and side berms.
- Pick up all discarded shotgun hulls on all bays and put them in the shotgun hull collection can by the pavilion that is clearly marked.
- Clean up the front gate area.
- Pick up and dispose of all garbage and material by the front gate.
- Trim weeds and make the entrance to the range look good.
- Fill in low spots from the paved road to the dirt road with dirt or gravel from the range that we will have on site.
- There is a safety table just inside of the front gate that is the “Designated” area for unloading/loading your carry gun when you enter/leave leave the range. This table needs to be painted and have a sign designating its purpose for all to see clearly.
- There is a drainage ditch that runs from the Outhouse Bay to the south berm, there are pipes that drain the range of water that need to be cleared out on a regular basis.
- Clean out the drainage ditch of any debris.
- Pipes running under the road to the courthouse bay need to be clean and free of obstructions on both sides and need to have a hole dug if front of both ends of the drain pipes.
- Exit pipe in the ditch at the south end of the range needs to be clear of any debris and have a have a hole dug in front of the drain.
- Walk the range and return props to their proper home.
- Barrels, Cowboy steel on the Courthouse, target stands and other miscellaneous items need to be returned to where they belong each week.
- All railroad ties around the main drainage ditch have floated out of place and need to be put back around the drainage ditch.
- All railroad ties need to be straightened and leveled throughout range.
- Outhouse on the Outhouse Bay is being used as a storage shed and needs to be cleaned out and repaired form wind damage.
- Silver Connex on the North side of the classroom is a junk yard that needs to be cleaned up.
- All lumber, pallets etc. that are still useful need to be saved but should be stacked and organized in a central location.
- Mine Shaft tin roof needs to be repaired or replaced.
- Junk yard at the far East end of the range needs to be cleaned up.
- Clean out all of the tumbleweeds and overgrown weeds.
- Throw away anything unneeded junk. (If dumpster is full, please report.)
- Organize and stack any useful material.
- Loading Tables
- Repair/replace all loading table tops and reinforce centers.
- Rebuild/repair all roofs.
- Repair and restack rocks and railroad ties at beginning of all berms.
- Blue Bell Chapel Bay
- Chapel needs new paint.
- Fence in front needs repair and new paint.
- There is a big hole in the roof that should be patched.
- Pull down any remaining ceiling or wall boards to leave the studs exposed, right now it’s about half and half and looks bad.
- Repair/reinforce railroad tie berm.
- Build a new coffin at front door (paint in corresponding color).
- Bank Bay
- Repair window bars.
- Repair safe surround.
- Repair swinging doors.
- Repaint as needed.
- Mine bay
- Repair and straighten several railroad tie walls.
- Rebuild or discard railroad tie shaft at end of bay.
- Close off side tunnel.
- Train Bay
- Move train.
- Repaint ticket booth and surrounding props.
- Reinforce railroad tie walls between bays.
- Clean up entrance to buried trailer.
- Dry Goods bay
- Reinforce fold down windows with new hinges.
- Paint
- Discard destroyed railroad ties in dumpster.
- Stagecoach Bay
- Stack railroad ties and clean up entrance to buried trailer.
- Hotel Bay
- Remove railroad ties in ground.
- Jail Bay
- Remove and replace corrugated metal with wood slats from exterior of jail.
- Repair window and door hinges.
- Repair rain gutter.
- Reinforce interior side table tops.
- Remove gun drop buckets.
- Cemetery Bay
- Remake grave marker around posts.
- Rework berm ends with rock and railroad ties.
- Courthouse Bay
- Fake brick façade on the front of the courthouse needs to be re-attached and fixed.
- Either repair or dispose of broken spools.
- Repair or add rain gutter.
- 75 Yard Bay (Gallows)
- Repair/maintain steel plate rack.
- Remove all rocks from bay.
- 100 Yard Bay
- Remove all rocks/bricks/blocks from bay.